Description
A bridge girder was locally damaged by road traffic and prestrssed strands were damaged. Within two hours the reinforcement was performed with re-plate. The …
Description
In the framework of a general renovation of an industrial facility, re-plate (in total over 250 m) strips were used as a flexural strengthening …
Description
In the framework of a seismic strengthening re-plates were installed for a monolithic connection between two slab parts. Prior tot he strengthening, the dilatation …
Project description
As part of a renovation project, new column supports were installed in the basement of the Kasinopark. In order to compensate for the …
Project description
As part of a renovation project, new recesses were reinforced over 14 floors. With the pre-stressed re-plate laminae an optimal load redistribution could …
Project description
The reinforced concrete ceiling (material storage of a carpentry) with thickness of 24 cm had to be strengthened because of a reconstruction. Therefore, …