Vault strengthening at the underground station Jungfraujoch

Jungfraujoch BE, Switzerland

Description
In the framework of several extension works in the underground railway station at the Jungfraujoch, re-bars were embedded in a sprayed mortar layer to strengthen a vault. Platform 3 currently offers only a one-side non disability-friendly access. With an extension of the station hall, new platforms will be constructed as well as the new station better adapted for shorter turnaround time spans. The extension of the platform access will also improve the visitor streams, which will also be separated from the freight traffic. Due to the mentioned extension of the access, the existing vault had to be strengthened in flexure in longitudinal direction. re-bars were anchored at both ends in a dry sprayed mortar layer over a length of about 1.5 m. After a sufficient cure, the bars were activated and hence prestressed over their free length., Finally, the complete remaining free length was covered with a Sika®Rock Gunit BE-8 mortar.

re-fer Product
15 memory-steel rebars with a length of 10 m anchored in sprayed mortar and ativated.

 

Year
2019

Contractor
re-fer AG

Info
Vault strengthening (Flexural strengthening)

Engineering consultant
B+S Ingenieure

 

Scroll To Top